top of page

Client: City of Doral
Duration: 270 days
Completion: April 2018
The City of Doral Canal Bank Stabilization Year 5a project uses geoweb panels to stabilize about 8500 LF of bank along the Dressel's Dairy Canal that have severely eroded. It also includes a 2400' long x 10' wide bike path and beautiful landscaping adjacent to the canal, providing a pleasant place for residents to enjoy.
​

Installation of geoweb panels

Water-side work

Asphalt Pedestrian Path

Installation of geoweb panels
1/4
Canal Bank Stabilization - Year 5a
bottom of page